PMP 1 Posted by PMHouse Date January 6, 2024 Comments 0 commentTry the full PMP® exam simulator (PMBOK® 8) — or join the PMI-authorized PMP course → Welcome to your PMP 1Which conflict resolution technique did the project manager use?On a refinery revamp in Kuwait, the mechanical and electrical managers both need the only certified rotating-equipment specialist during the same three weeks. After a tense meeting, the project manager proposes that each manager give up part of the time they requested so both work fronts can continue. Neither manager gets the full schedule they wanted, but both accept the arrangement and the shutdown stays on track. Compromise, in which each party gives up something so that a partly satisfying solution is reached. Collaboration, in which the parties work through their interests to reach a fully shared solution. Smoothing, in which areas of agreement are stressed and the differences between parties are played down. Forcing, in which one party's preference is imposed by the authority of the person making the decision. None What should the scrum master do?A product team at a telecom company in Kuwait has seen rising overtime and two resignations in six months, yet the annual company survey showed nothing unusual. In a retrospective, members propose a short monthly pulse survey to track team satisfaction trends, workload and growth. Some members worry that answers could be traced back to individuals in a team of only nine people. Rely on the annual company survey, since a separate team survey duplicates effort and may confuse the HR department's data. Implement a short anonymous pulse survey, share only aggregated trends, and let the team discuss the results and agree actions. Ask each member to rate satisfaction openly at the start of every retrospective so that issues can be discussed right away. Collect individual monthly survey responses and review them privately with each member during one-on-one meetings. None What should the project manager do?Two weeks before the go-live of a new payroll system for a ministry in Amman, the ministry's HR director has become short-tempered in meetings, criticizing the team sharply over minor issues. The project manager learns from a colleague that the director is under heavy pressure from senior leadership about the deadline and is also dealing with a family illness. The team is becoming defensive. Ask the sponsor to speak to the director about his behavior, since it is affecting the team's morale before go-live. Reduce contact with the director until go-live and send him only written status updates to avoid further tension. Meet the director privately, show empathy, and offer practical ways to reduce his burden while keeping him informed. Address the criticism point by point in the next meeting so that the team's work is defended in front of everyone. None What should the project manager do?Sara, a planning engineer on a metro project in Riyadh, asks the project manager to mentor her because she wants to become a project manager within three years. The project manager's calendar is already full with client meetings and contractor reviews. Sara is a strong performer, and the PMO has said that building internal project management capability is a priority for the year. Refer her to the PMO's formal training catalogue, since a full calendar leaves no room for regular mentoring sessions. Agree to mentor her once the current project phase ends, when the calendar is expected to be less demanding. Ask a senior planning engineer on the team to mentor her, since he knows her day-to-day work better than anyone else. Agree a short fortnightly session with her and add shadowing and stretch tasks that fit into the project's normal work. None What should the Scrum Master do?A Scrum team designing a diabetes self-care app for a health ministry in Oman has a senior clinician from the client embedded for user research input. Her clinical insight is excellent, but in refinement sessions she speaks first and at length, and team members now defer to her instead of proposing ideas. The product owner values her input and wants to keep her engaged. Talk privately with the clinician, and agree on a session format where she shares context before the team proposes ideas. Ask the product owner to limit the clinician's attendance to sprint reviews, so the team can refine the backlog on its own. Let the current pattern continue, since the clinician's insight is more reliable than the team's ideas on clinical matters. Remind the whole team in the next session that everyone must speak up, and call on quieter members by name more often. None What should the project manager do first?Midway through a two-year warehouse automation project for a food distributor in Saudi Arabia, the company launches three strategic initiatives: a sustainability program, a data analytics platform, and a customer self-service portal. Each initiative leader asks the project manager to adjust the project to align with their goals. Two requests would add significant scope, and one directly conflicts with the approved conveyor design. Agree to all three requests in principle to show strategic support and work out the details in later phases. Review the requests with the sponsor against the project's objectives and agree which ones to pursue. Decline all three requests politely, explaining that the approved scope cannot change once execution starts. Submit three change requests to the change control board and let the board decide each one on its merits. None What should the project manager do?A national e-government program in Kuwait sends a weekly newsletter to 50 stakeholders, as defined in the communications management plan. Analytics show only about 20% open it, and two directors recently said they were unaware of a key decision that appeared in it. The newsletter is a four-page document covering every workstream in equal detail. Stakeholders range from ministers' advisors to technical leads in partner agencies. Ask the sponsor to send a memo instructing all stakeholders to read the newsletter each week and confirm receipt of it. Increase the newsletter to twice a week so key decisions reach stakeholders sooner and are less likely to be missed. Survey stakeholder groups on their information needs and tailor content, format, and channel for each group's use. Shorten the newsletter to one page with a decisions box at the top and keep sending the same version to all of them. None Which action should the project manager support?A new cross-functional team has been formed from three departments to build a digital permits service for a municipality in Sharjah. Members still introduce themselves by their home departments, and hand-offs between them are slow. A developer suggests creating a team name, a shared purpose statement and branded items. The sponsor supports team identity but wants it to help the delivery goal. Ask the sponsor to choose a team name and slogan so the identity reflects leadership's vision for the permits service. Order branded items for the team right away since a visible identity will quickly replace the department loyalties. Postpone any team identity activity until after the first release so that the team stays focused on its delivery. Facilitate a workshop where the team defines its purpose around the permits outcome, then picks its identity. None What should the project manager do?During a site visit to a metro station project in Riyadh, the client's representative loudly criticizes a young site engineer in front of the crew for a delayed inspection report, using demeaning language. The delay was actually caused by late test results from a third-party laboratory. The engineer is visibly shaken. The project manager, who is present, values the client relationship and the contract is entering a sensitive variation negotiation. Calmly redirect the conversation, explain the lab delay, then support the engineer and give the client private feedback. Ask the engineer to apologize to the representative now so the client relationship stays positive during the negotiation. Stay silent during the visit and later email the representative's manager a formal complaint about the incident. Let the incident pass without comment, since the variation negotiation is more important to the project right now. None Which Tuckman stage is the team in, and what should the project manager do?An Egyptian telecom operator has formed an eight-person cross-functional team from finance, IT, operations and marketing for an 18-month digital transformation project. None of the members have worked together before. Two weeks in, the project manager notices that meetings are polite and orderly, but people avoid stating strong opinions, look to the project manager for direction and are unsure how their roles fit together. Norming, so the project manager should step back and let members organise their own work and decision making. Forming, so the project manager should clarify roles, build relationships and agree a team charter with members. Storming, so the project manager should mediate disagreements early before they escalate into open conflict. Performing, so the project manager should delegate fully and focus on stakeholder management outside the team. None What should the project manager do?At a sprint review for a logistics tracking platform in Riyadh, the operations director asks the team to deliver five new dashboard features in the next two-week sprint ahead of a board meeting. The team's velocity over the last six sprints shows they complete two to three features of this size per sprint. The director is influential and visibly frustrated by the current pace. The product owner is in the room. Accept the five features for the sprint and plan overtime so the director has everything before the board meeting. Explain that the sprint is already planned and ask the director to submit the request through change control. Share the velocity data openly and ask the product owner to agree with the director which features matter most. Commit to three features now and promise the remaining two will be delivered in the following sprint. None What should the project manager do first?A refinery maintenance management project in Yanbu is entering closure. Three specialists who configured the work-order and spare-parts modules have already been released to a new project before completing knowledge transfer to the client's operations team. The sponsor wants a clean handover in four weeks, and the operations supervisor says his staff cannot support the modules without walkthroughs. The specialists' new project manager is under deadline pressure. Ask the operations supervisor to have his team learn the modules from the user manuals over the next weeks. Escalate to the sponsor and request that the three specialists be recalled full-time until closure is done. Close the project on schedule and log the incomplete knowledge transfer as a lesson learned for future work. Agree with the specialists' new manager on short scheduled sessions to transfer the critical module knowledge. None How should the project manager classify the product owner?A project manager at a healthcare software company in Dubai is analyzing stakeholders for a new patient portal. The newly assigned product owner has formal authority to accept or reject every increment, insists that certain compliance features be addressed in the current sprint, and is recognized by the board as the rightful decision-maker on product scope. The project manager plans to use the salience model. Classify the product owner as definitive, holding power, urgency and legitimacy, and engage him very closely. Classify the product owner as dominant, holding power and legitimacy but no urgency, and keep him satisfied. Classify the product owner as dangerous, holding power and urgency but no legitimacy, and monitor him closely. Classify the product owner as demanding, holding urgency only, and give him updates when time is available. None What should the project manager do first?Halfway through a digital customer-onboarding program at a bank in Casablanca, a reorganization replaces the sponsor. The new sponsor, from the retail division, has different priorities and asks to review all major decisions taken so far, including the vendor selection and the phased release plan. The team is concerned that previously agreed scope will be reopened and work will stall while the review takes place. Explain to the new sponsor that the steering committee has already approved these decisions and they cannot be reopened Brief the new sponsor on the business case, key decisions and rationale, status, and risks, and record any new direction Pause the vendor and release workstreams until the new sponsor completes the review to avoid rework on reversed decisions Ask the previous sponsor to remain involved informally so that the original direction is preserved during the transition None What should the project manager do?On a highway expansion project in Oman, the client's deputy project director replies to all on nearly every email, adding comments to threads that include forty recipients from five contractors. Engineers report that important instructions are buried in long threads, and one site team missed a revised traffic diversion plan last week. The communications management plan does not define distribution lists or channels. Ask the deputy director privately to stop replying to all, since his emails are the main cause of the overloaded threads. Advise engineers to set inbox filters so that emails from long threads are moved to a separate folder and read when time allows. Update the communications plan with distribution lists and a formal channel for instructions, agreed with the deputy. Send all forty recipients a reminder of good email etiquette and ask them to reply only to the sender unless others need to know. None What should the project manager do?A developer on an e-government portal team in Bahrain has an idea for an AI-based form assistant that could cut citizens' completion time. The feature does not match the product vision the sponsor approved, which prioritises accessibility and simplicity. The developer asks the project manager to let him build it quietly during the sprint, arguing that the sponsor will not notice and will like the result. Let him build a small prototype within the sprint, then show the sponsor if it turns out to work well. Reject the idea, explaining that the approved product vision has already set the priorities for the portal. Report the request to his functional manager as an attempt to work outside the agreed sprint commitments. Decline the hidden build and help him present the idea and its value to the product owner and sponsor. None Which approach should the project manager use?On a metro station project in Riyadh, two senior structural engineers strongly disagree on whether to use precast or cast-in-place concourse slabs. Each has solid data, the debate has become personal in coordination meetings, and the design freeze date is three weeks away. The project manager wants a durable decision that draws on both engineers' expertise and that both will commit to during construction. Facilitate a joint problem-solving session that examines both sets of data against agreed criteria to reach consensus. Make the decision personally based on which option best protects the design freeze date, and then inform both engineers. Ask each engineer to give up part of their proposal so the team can reach a middle-ground design within the week. Emphasize the points on which both engineers already agree and ask them to set the remaining differences aside. None Which estimate at completion should the project manager report?A contractor is building a desalination intake structure in Yanbu with a budget at completion of $2,000,000. At the latest status date, earned value is $900,000, actual cost is $1,000,000 and planned value is $1,000,000. The sponsor believes both the cost overrun and the schedule slippage are systemic and will continue, because the remaining marine works depend on the same crews and weather windows. She asks for an estimate at completion. Report an EAC of about $2,469,000, dividing the budget at completion by the product of CPI and SPI. Report an EAC of about $2,358,000, adding the remaining work divided by CPI times SPI to the actual cost. Report an EAC of about $2,222,000, dividing the budget at completion by the cost performance index. Report an EAC of about $2,100,000, adding the remaining budgeted work at original rates to actual cost. None Which estimation technique is the team using?An e-learning company in Amman is preparing release planning for a new course-authoring tool. The product owner has just prioritized 40 new user stories, and the team has only one hour to produce rough estimates so the release roadmap can be shared with clients. Rather than numbers, team members place each story into one of five size buckets, XS to XL, by comparing it with stories they have already delivered. Planning poker, revealing Fibonacci-numbered cards at the same time and discussing differences in estimates. Analogous estimating, scaling the actual hours of a similar past project to forecast the new tool's duration. Relative sizing with T-shirt sizes, comparing each story's effort with others rather than estimating hours. Bottom-up estimating, decomposing each story into tasks and summing the estimated hours for every task. None What should the project manager do?On an ERP rollout for a logistics group in Dubai, the lead integration engineer tells the project manager that she has worked about 60 hours a week for three months to keep up. Her recent code reviews show a rising defect rate, and two other engineers report similar hours. The resource histogram shows integration demand at 140% of available capacity for the next two months, and the go-live date is contractually fixed. Approve paid overtime for the integration engineers until go-live so that their extra hours are recognized. Ask the engineers to focus on the critical-path work only and defer all code reviews until after go-live. Assign the engineer to lighter tasks for two weeks and redistribute her current work among the other two. Analyze the capacity gap and give the sponsor options such as added resources or reprioritized scope. None What should the project manager advise?A ministry of health in Amman has issued an RFP for a hospital laboratory information system. The RFP requires three client references for similar implementations and allows the committee to seek clarification or equivalent evidence through the procurement office. One technically strong bidder declines, stating that its clients are bound by confidentiality, while the other four bidders have submitted references. Bid evaluation is scheduled for next week, and the evaluation committee asks the project manager how to treat this bid. Ask the bidder, via procurement, for acceptable alternatives such as redacted case studies or a site visit. Disqualify the bid immediately, since the bidder has not met a mandatory requirement stated in the RFP. Waive the reference requirement for this bidder, since its technical proposal is clearly the strongest of all five. Ask a committee member to contact the bidder's known clients informally to check its record of performance. None What should the project manager do with the open risks?An agile team at a university in Jordan has finished the last iteration of a new HR self-service portal. The product owner confirms that all prioritized backlog items meet the definition of done, and the sponsor is ready to close the project. The risk register still lists three open risks: a pending payroll interface upgrade, a licence renewal next year, and low adoption among part-time staff. Close the open risks in the register because the project has delivered all of its committed scope. Agree with the owners which risks to accept and hand over the rest to operations with clear owners. Keep the project open until each of the three risks has either occurred or been fully resolved. Transfer the open risks to an insurer so that the university is protected after the team disbands. None What should the project manager do next?A hospital information system in Amman is delivered with a hybrid approach. The infrastructure team follows a predictive plan with formal sign-off gates, while two application teams work in two-week sprints. At the first integration point, the application teams wait two weeks for server environment sign-off, and their sprint goals slip. Each side blames the other's method, and the sponsor asks the project manager how integration will work for the rest of the project. Move the infrastructure team into sprints so that all teams share one cadence and one backlog for the rest of the project. Ask the application teams to follow the infrastructure gate plan and schedule their sprints around each formal sign-off. Redesign the integration points with both leads, aligning sign-off timing and environment handoffs to the sprint cadence. Add a two-week buffer before each integration point in the master schedule to absorb the infrastructure sign-off time. None Which interpretation should the project manager present?A contractor is upgrading a water treatment plant in Alexandria. At the month-six status date, the planned value is EGP 4.5 million, the earned value is EGP 4.0 million, and the actual cost is EGP 3.7 million. The utility's steering committee asks the project manager to explain what these figures mean before it decides whether to approve overtime for the remaining mechanical works. The project is ahead of schedule but over budget, so tighten cost controls before releasing any additional funds. The project is behind schedule and over budget, so request a formal re-baseline of both the schedule and the cost plan. The project is under budget and on schedule, so report healthy performance and decline the overtime request. The project is behind schedule but under budget, so investigate why progress lags before approving overtime spending. None Which action best addresses the team's concern?An agile team at a retail bank in Cairo has delivered mobile onboarding features for six sprints. In the retrospective, developers say they no longer know whether their work matters because they only see velocity charts. The product owner has analytics showing that digital account openings rose 18 percent, but this data has never been shared with the team. The sponsor wants the team to stay focused on customer outcomes. Add a section to each sprint review where the product owner shares outcome data and customer feedback. Replace velocity with story points completed per developer so that individual contributions become visible. Ask the sponsor to send the team a quarterly email summarizing how the program supports the bank's strategy. Publish the analytics dashboard link on the team wiki so developers can check business results when they wish. None What should the project manager do?A contractor delivers a pharmacy automation system to a hospital in Kuwait. The system passed all internal QA tests, but during customer acceptance testing the hospital finds two critical defects: incorrect dosage rounding and a label printing failure. The hospital refuses to sign acceptance. The contractor's QA lead says the defects came from test data the hospital supplied late, and the account manager wants to argue the point. Ask the hospital to sign a conditional acceptance now and commit to fixing both defects during the warranty period. Acknowledge the defects, fix and retest them with the hospital, and analyze why internal QA failed to catch them. Present evidence that the late test data caused the defects and ask the hospital to share the cost of the corrections. Escalate the dispute to the contract managers on both sides so that the responsibility for the defects can be settled. None How should the project manager respond?A university in Jeddah is deploying a new student information system. The data-center hardware installation follows a predictive plan with an approved WBS, while the software configuration is delivered in two-week sprints from a product backlog. At a steering committee meeting, the sponsor asks the project manager to present the scope baseline so the committee can track scope changes for the remainder of the project. Present the product backlog as the single scope reference, since hybrid delivery replaces the WBS in both streams. Present a newly baselined WBS covering both streams so the committee can control every scope change in one place. Present the approved WBS baseline for the hardware stream and the prioritized product backlog for the software stream. Explain that hybrid projects do not use a scope baseline and that scope is instead reviewed at every sprint review. None What is the cost performance index (CPI) for this sprint?A Scrum team at a bank in Bahrain is tracking release finances with agile earned value. For the current sprint, the team planned 50 story points with a budget of $1,000 per point, so planned value is $50,000. Labor costs for the sprint came to $55,000. At the sprint review, the product owner accepted 40 story points as done; the other 10 points failed acceptance tests and returned to the backlog. CPI is about 0.91, because planned value of $50,000 is divided by the actual cost of $55,000 spent. CPI is 0.80, because earned value of $40,000 is divided by the planned value of $50,000 for the sprint. CPI is 1.10, because the actual cost of $55,000 is divided by the planned value of $50,000 for the sprint. CPI is about 0.73, because earned value of $40,000 is divided by the actual cost of $55,000 spent. None How should the project manager respond?On a hospital extension project in Dammam, the structural steel erection activity has been delayed by three days because the inspection authority rescheduled its visit. The activity lies on the critical path and has zero total float. The approved completion date is fixed in the contract, and the next critical activities are cladding and roofing. The client asks the project manager what the delay means for the completion date. Advise that completion is forecast to slip three days and evaluate crashing or fast-tracking the next critical activities. Advise that completion is unaffected because the project-level schedule reserve will absorb the three-day delay. Advise that completion will slip by more than three days since every successor activity will now shift as well. Advise that completion is unaffected as long as non-critical activities with free float are started earlier. None What should the project manager do?A business analyst on a pension-system modernization in Muscat has a long-planned family vacation that overlaps the next sprint review. This review will show the first end-to-end calculation flow to the fund's board members, and she prepared most of the scenarios. The leave was approved months ago under company policy. The project manager is concerned that the demonstration will be weaker without her. Ask her to shorten the vacation by a few days so that she can attend the board demonstration and present her scenarios herself. Honor the approved leave and plan coverage, such as a walkthrough of her scenarios with a colleague who will present them. Move the sprint review to the week after her return so that the board sees the demonstration with the full team present. Ask her to join the review remotely from her vacation for the part covering her scenarios, since the board meeting is important. None What should the project manager do next?A logistics company in Alexandria licenses a route-planning platform at a per-user rate. The original agreement covered 10 users, but the rollout to regional depots will raise usage to 50 users within six months, multiplying the annual license cost by five. The contract renewal date is three months away, and two competing platforms offer enterprise pricing. The finance manager wants a recommendation. Approve the additional user licenses now at the current rate so that the regional rollout is not delayed by contract talks. Recommend switching to the competing platform with the lowest enterprise price before the current contract renews. Work with procurement to renegotiate volume or enterprise terms, using the alternatives to evaluate leverage and lock-in. Limit the rollout to the original 10 users and ask depots to share accounts until the renewal date has been reached. None What should the project manager do?A water treatment SCADA upgrade in Sharjah is 95% complete. The remaining work is the as-built documentation, operating manuals, and handover training records listed in the contract's acceptance criteria. The team, eager to move to a new project, argues that the real work is done and the client's operators already know the system. The client's maintenance manager has asked twice when the manuals will arrive. Release most of the team to the new project and leave one engineer to finish the manuals over the coming months. Ask the client to sign acceptance now and deliver the documentation later as a separate, low-priority follow-up item. Provide short summary guides instead of full manuals so the team can finish quickly and still close out the project. Keep the team focused on completing the documentation, since it is a contractual deliverable required for acceptance. None Why is the architect's approach the better delivery choice?A team at a Qatari airline is starting a new baggage-tracking feature that touches the mobile app, a new API layer, the legacy reservation system, and airport scanners. Integration across these layers has caused late failures on past projects. In sprint planning, the architect proposes beginning with a walking skeleton. Some developers prefer to build and perfect each layer separately before connecting them. It builds a thin end-to-end slice through all layers early, proving integration before features are fleshed out. It completes the full architecture design up front so that each layer can then be built without later rework. It delivers a clickable prototype of the app screens so that users can approve the interface before coding begins. It assigns each layer to a separate sub-team so that all layers progress in parallel and are joined at the end. None How should the project manager prepare the interim review?A 30-month metro station package in Jeddah has just reached 50 percent of its baseline duration. The sponsor has requested a formal interim review to decide whether to release the next funding tranche. The project manager has strong cost data showing a CPI of 0.98, but schedule, quality and risk information sit in separate reports owned by different leads, and the benefits forecast has not been updated since the business case was approved. Focus the review on the cost position, since a CPI of 0.98 is the main evidence the sponsor needs for the funding tranche. Integrate scope, schedule, cost, quality, risk and benefit forecasts against the baselines into one decision-ready view. Ask each lead to present their own report in sequence and let the sponsor draw conclusions from the separate inputs. Postpone the review until the benefits forecast is refreshed, so the sponsor receives a complete business case update. None What should the project manager do?A ministry of health in the Gulf is deploying a new electronic prescribing system to 120 clinics. The business case projects savings from fewer dispensing errors, but only if pharmacists and physicians use the system correctly from day one. The training budget of USD 180,000 was cut during the annual budget review, and clinic managers warn that without it adoption will be patchy. Go-live is four months away. Proceed with go-live and rely on clinic managers to train their own staff using the vendor's standard user guides. Reallocate USD 180,000 from the project's contingency reserve to restore the training plan without delaying go-live. Show the sponsor how the training cut threatens the projected benefits and present lower-cost training options. Postpone go-live until the next budget cycle, when the training funding can be requested again through normal channels. None What should the Scrum Master do?An internal quality audit at a Qatari insurance company reviewed the last three sprints of a claims-portal team. It found that some stories were marked done once coded, while others were marked done only after testing and deployment to staging. As a result, the sprint review showed features as complete that stakeholders could not use, and the product owner's release forecasts have been unreliable for a month. Ask the auditor to specify the definition of done the team should follow so that it matches the company's quality policy. Let each developer keep a personal definition of done but ask them to label stories clearly as coded or as deployed. Report only deployed stories as done from now on and let the product owner adjust past velocity figures for the forecast. Facilitate the team in agreeing one shared definition of done and re-check the stories already reported as complete. None What should the project manager do?A food manufacturer in Jeddah contracted a vendor to supply and install an inventory tracking system. The vendor delivered exactly what the signed statement of work described, and every acceptance test passed. However, warehouse supervisors now say the system cannot handle batch and expiry-date tracking, which they consider essential. The project manager confirms that this need never appeared in the requirements documentation or the statement of work. Raise a change request for batch and expiry tracking and record the requirements gap as a lesson for future elicitation. Ask the vendor to add batch and expiry tracking at no extra cost, since the system does not meet the business need. Withhold the final payment until the vendor and supervisors agree on how batch and expiry tracking will be provided. Ask the supervisors to track batches and expiry dates in spreadsheets, since the delivered system met the contract terms. None What should the project manager do next?A utility in Amman is midway through a predictive project to replace its meter-reading system under an approved scope baseline. A technical study completed this month shows that a newly available smart-meter platform makes roughly 30% of the planned customizations unnecessary. The contractor is still building some of those components. The project manager estimates that dropping them could save cost and two months, though contract terms may require compensation for work already started. Instruct the contractor to stop work on the affected components immediately to avoid spending more on unneeded work. Analyze the affected components and their contract impact, then submit a change request with options to the change board. Continue delivering the approved baseline and record the study's findings as a lesson learned for future projects. Update the scope baseline to remove the components and inform the sponsor of the expected savings in the next monthly report. None What should the project manager do next?An agile team is building a citizen services portal for a government authority in the GCC. National digital-government regulations require public portals to meet a defined web accessibility conformance level. At the sprint review, a ministry representative asks whether the new booking feature complies, and the team realizes accessibility was never part of its acceptance criteria. Four sprints remain before the public launch date set by the authority. Commission an external accessibility audit after the public launch and fix any findings in a later maintenance release. Ask the product owner to create a single accessibility epic and schedule it in the release that follows the launch. Confirm the required conformance level, assess delivered features against it, and add it to the Definition of Done. Assure the ministry that the UI framework the team uses already handles accessibility for all of its standard screens. None What should the project manager do?After a payment outage at a digital wallet provider in Cairo, the operations director wants to identify the engineer who pushed the faulty configuration. A senior team member proposes running a blameless post-incident review instead, focusing on which system conditions allowed the error. Engineers have been reluctant to report near misses since a colleague was formally reprimanded after a previous incident. Identify the engineer responsible first so that the director is satisfied, then run a blameless review on the remaining causes. Run the review privately with senior engineers only so that junior staff do not feel exposed during the discussion. Add a mandatory second approval to all configuration changes and skip the review, since the immediate cause is already known. Support a blameless review focused on system causes, agree owners for the actions, and explain the approach to the director. None What should the project manager do first?A petrochemical company in Jubail is upgrading its plant control system over eighteen months. The operations vice president, who chairs the design authority and approves every major technical decision, has privately told the project manager that he is likely to retire in about three months. No deputy has been named, and several design decisions planned for month five depend on his judgment and his knowledge of past plant incidents. Record the risk and agree responses with the sponsor, such as capturing his rationale and naming a successor. Ask the vice president to delay his retirement until the critical design decisions have been approved in full. Bring the month-five design decisions forward to next month so that he can approve them before he retires. Wait until the retirement is officially announced before updating the plan, since the information is private. None What should the Scrum Master do?A newly hired developer at a software house in Amman proposes that the team move to a four-day work week, citing studies on productivity and wellbeing. Several senior members worry about customer support coverage and contract commitments. The company has no policy on compressed schedules, and the CEO has said leadership is open to well-evidenced proposals for new ways of working. Allow the team to start a four-day week trial next sprint, since self-managing teams can decide their working hours. Help the team prepare a proposal for leadership with a measured pilot that addresses support and contract concerns. Decline the proposal, since the company has no policy on compressed schedules and senior members are concerned. Ask HR to research four-day week policies in other companies and report back before the team discusses it again. None What should the project manager do?A hybrid team rolling out a patient-portal for a hospital group in Saudi Arabia keeps waiting on decisions from the executive committee, such as data-retention rules and vendor selection for SMS notifications. Recent decisions have taken three to five weeks, and two sprints have had to swap in lower-value work. At the retrospective, the team says leadership is too slow and the delays are hurting delivery. Escalate the delays to the hospital group's CEO and request that the executive committee meet weekly until pending decisions clear. Make the pending decisions on the committee's behalf and inform it afterward, since the delays are harming delivery. Bring the committee concise options with a recommendation and needed-by dates, and agree which decisions the team can own. Record the waiting time in the issue log and report the cumulative delay at the end of each phase to the committee. None What should the project manager do first?A project manager is leading an ERP rollout for a manufacturing group in Amman when the group announces a merger with a larger regional competitor. The project's sponsor will leave after the merger closes next month, and the combined company will review all capital projects. Team members are anxious about their jobs, and two vendors have asked whether their contracts will be honored. Accelerate the rollout so that key modules go live under the current sponsor before the merger closes next month. Pause all project activities until the combined company's leadership confirms whether the ERP rollout will continue at all. Assure the team and vendors that the project will continue unchanged, since the current sponsor has approved the full budget. Assess the merger's impact on the business case and prepare a status and value summary for the incoming leadership's review. None What should the project manager do?In a retrospective, an agile team at a software firm in Cairo votes unanimously to trial a four-day work week, citing burnout and strong recent delivery. The firm's HR policy sets a standard five-day week for all employees, and changes require executive approval. Team members ask the project manager to simply let them start next sprint, saying their velocity will prove the idea works. Present a pilot proposal with success measures to the executives who own the policy, and share their decision with the team. Let the team start the trial next sprint, since self-organizing teams should decide how they work as long as delivery is maintained. Tell the team that working-time policy is outside the project's scope and move the retrospective on to other improvement items. Allow the team to work longer hours on four days informally, so the policy is respected on paper while the team gets its extra day. None What should the project manager do next?On a predictive water-treatment plant expansion in Alexandria, the change control board approves a change that relocates the chemical dosing building to meet a new setback rule. The project manager updates the drawings register, the scope statement and the schedule and cost baselines. The civil subcontractor's crew is due on site in three days, and the procurement lead and the client's operations team still hold copies of the old layout and the old delivery dates. Let the subcontractor begin on site and monitor the change through the next weekly progress report. Communicate the approved change to affected stakeholders and adjust responsibilities before work starts. Return the change to the change control board for a second review of the updated cost baseline figures. Prepare a revised project charter that reflects the new building location for the sponsor's formal signature. None What should the project manager do immediately?A project manager at a fintech company in Dubai discovers that the lead engineer of an outsourced development vendor has posted code from the company's proprietary payments engine in his public online portfolio. The vendor contract includes confidentiality and intellectual property clauses, and the company has a legal department. The posts are still publicly visible, and the vendor's team is midway through the current release. Contact the engineer directly and ask him to remove the code from his portfolio before the matter is escalated Suspend the vendor's access to all repositories and stop the release until the vendor explains what happened Record evidence of the posts, involve the legal department, and notify the vendor formally under the contract Post a public comment on the portfolio stating that the code is proprietary and must be removed at once None What should the project manager do?A cloud operations team at a bank in Abu Dhabi recently adopted blameless post-incident reviews. Last week, a configuration change by one engineer caused a two-hour outage of the mobile banking app. At the first review, the engineer looks tense, and a manager from another department has already asked in the chat who made the change. The project manager is facilitating the session. Ask the engineer to explain the configuration change first so the team understands exactly what went wrong in the outage. Reply privately to the manager that names will not be shared and then continue the review without mentioning the question. Postpone the review until the engineer feels more comfortable so that the discussion can take place in a calmer setting. Restate that the review seeks system causes, not blame, and guide questions toward the gaps that let the change fail. None What should the project manager do?The sponsor of a national railway signalling upgrade is preparing the annual board presentation. She asks the project manager to delete three high-rated risks from the formal risk register before it is shared, arguing that board members will not understand the technical nuance and might cut funding. The risks are real, have named owners and active mitigation plans. The board pack is due in two days. Keep the risks in the register and offer the sponsor a clear board summary showing each owner and mitigation. Remove the three risks from the board version only, while keeping them in the working register the team uses daily. Remove the risks as requested, since the sponsor is accountable for the information that goes to the board. Report the sponsor's request to the PMO director at once and ask the PMO to take over the board submission. None What should the Scrum Master do first?Six months into an agile transformation at a government housing agency in Riyadh, most delivery team members have adopted the new practices. Two experienced analysts still write full specifications up front and skip refinement sessions, saying the old method has always worked. Their work is delaying feedback on two features, and other members are growing frustrated with them. Ask their manager to require attendance at refinement sessions, since the agency has formally adopted the agile approach. Meet each analyst privately to understand the source of their resistance, then address it with evidence or support. Allow them to continue their method, as long as their specifications arrive before the sprint that needs them for work. Raise the issue in the next retrospective so the team can tell the two analysts how their approach affects everyone else. None Time's upThis is a free 50-question sample.Unlock the full question bank: PMP® exam simulator (PMBOK® 8) →Share: PMHouse Previous post Sp 2 January 6, 2024Next post PRINCE 2 Exam1 January 6, 2024You may also like AI for Project Managers: 7 Practical Uses and PMI’s New Standard November 24, 2026 How to Set Up a PMO: A Step-by-Step Guide November 17, 2026 New PMP Exam 2026: What Changed and How to Prepare November 14, 2026