PMP 1

Welcome to your PMP 1

Which conflict resolution technique did the project manager use?

On a refinery revamp in Kuwait, the mechanical and electrical managers both need the only certified rotating-equipment specialist during the same three weeks. After a tense meeting, the project manager proposes that each manager give up part of the time they requested so both work fronts can continue. Neither manager gets the full schedule they wanted, but both accept the arrangement and the shutdown stays on track.

What should the scrum master do?

A product team at a telecom company in Kuwait has seen rising overtime and two resignations in six months, yet the annual company survey showed nothing unusual. In a retrospective, members propose a short monthly pulse survey to track team satisfaction trends, workload and growth. Some members worry that answers could be traced back to individuals in a team of only nine people.

What should the project manager do?

Two weeks before the go-live of a new payroll system for a ministry in Amman, the ministry's HR director has become short-tempered in meetings, criticizing the team sharply over minor issues. The project manager learns from a colleague that the director is under heavy pressure from senior leadership about the deadline and is also dealing with a family illness. The team is becoming defensive.

What should the project manager do?

Sara, a planning engineer on a metro project in Riyadh, asks the project manager to mentor her because she wants to become a project manager within three years. The project manager's calendar is already full with client meetings and contractor reviews. Sara is a strong performer, and the PMO has said that building internal project management capability is a priority for the year.

What should the Scrum Master do?

A Scrum team designing a diabetes self-care app for a health ministry in Oman has a senior clinician from the client embedded for user research input. Her clinical insight is excellent, but in refinement sessions she speaks first and at length, and team members now defer to her instead of proposing ideas. The product owner values her input and wants to keep her engaged.

What should the project manager do first?

Midway through a two-year warehouse automation project for a food distributor in Saudi Arabia, the company launches three strategic initiatives: a sustainability program, a data analytics platform, and a customer self-service portal. Each initiative leader asks the project manager to adjust the project to align with their goals. Two requests would add significant scope, and one directly conflicts with the approved conveyor design.

What should the project manager do?

A national e-government program in Kuwait sends a weekly newsletter to 50 stakeholders, as defined in the communications management plan. Analytics show only about 20% open it, and two directors recently said they were unaware of a key decision that appeared in it. The newsletter is a four-page document covering every workstream in equal detail. Stakeholders range from ministers' advisors to technical leads in partner agencies.

Which action should the project manager support?

A new cross-functional team has been formed from three departments to build a digital permits service for a municipality in Sharjah. Members still introduce themselves by their home departments, and hand-offs between them are slow. A developer suggests creating a team name, a shared purpose statement and branded items. The sponsor supports team identity but wants it to help the delivery goal.

What should the project manager do?

During a site visit to a metro station project in Riyadh, the client's representative loudly criticizes a young site engineer in front of the crew for a delayed inspection report, using demeaning language. The delay was actually caused by late test results from a third-party laboratory. The engineer is visibly shaken. The project manager, who is present, values the client relationship and the contract is entering a sensitive variation negotiation.

Which Tuckman stage is the team in, and what should the project manager do?

An Egyptian telecom operator has formed an eight-person cross-functional team from finance, IT, operations and marketing for an 18-month digital transformation project. None of the members have worked together before. Two weeks in, the project manager notices that meetings are polite and orderly, but people avoid stating strong opinions, look to the project manager for direction and are unsure how their roles fit together.

What should the project manager do?

At a sprint review for a logistics tracking platform in Riyadh, the operations director asks the team to deliver five new dashboard features in the next two-week sprint ahead of a board meeting. The team's velocity over the last six sprints shows they complete two to three features of this size per sprint. The director is influential and visibly frustrated by the current pace. The product owner is in the room.

What should the project manager do first?

A refinery maintenance management project in Yanbu is entering closure. Three specialists who configured the work-order and spare-parts modules have already been released to a new project before completing knowledge transfer to the client's operations team. The sponsor wants a clean handover in four weeks, and the operations supervisor says his staff cannot support the modules without walkthroughs. The specialists' new project manager is under deadline pressure.

How should the project manager classify the product owner?

A project manager at a healthcare software company in Dubai is analyzing stakeholders for a new patient portal. The newly assigned product owner has formal authority to accept or reject every increment, insists that certain compliance features be addressed in the current sprint, and is recognized by the board as the rightful decision-maker on product scope. The project manager plans to use the salience model.

What should the project manager do first?

Halfway through a digital customer-onboarding program at a bank in Casablanca, a reorganization replaces the sponsor. The new sponsor, from the retail division, has different priorities and asks to review all major decisions taken so far, including the vendor selection and the phased release plan. The team is concerned that previously agreed scope will be reopened and work will stall while the review takes place.

What should the project manager do?

On a highway expansion project in Oman, the client's deputy project director replies to all on nearly every email, adding comments to threads that include forty recipients from five contractors. Engineers report that important instructions are buried in long threads, and one site team missed a revised traffic diversion plan last week. The communications management plan does not define distribution lists or channels.

What should the project manager do?

A developer on an e-government portal team in Bahrain has an idea for an AI-based form assistant that could cut citizens' completion time. The feature does not match the product vision the sponsor approved, which prioritises accessibility and simplicity. The developer asks the project manager to let him build it quietly during the sprint, arguing that the sponsor will not notice and will like the result.

Which approach should the project manager use?

On a metro station project in Riyadh, two senior structural engineers strongly disagree on whether to use precast or cast-in-place concourse slabs. Each has solid data, the debate has become personal in coordination meetings, and the design freeze date is three weeks away. The project manager wants a durable decision that draws on both engineers' expertise and that both will commit to during construction.

Which estimate at completion should the project manager report?

A contractor is building a desalination intake structure in Yanbu with a budget at completion of $2,000,000. At the latest status date, earned value is $900,000, actual cost is $1,000,000 and planned value is $1,000,000. The sponsor believes both the cost overrun and the schedule slippage are systemic and will continue, because the remaining marine works depend on the same crews and weather windows. She asks for an estimate at completion.

Which estimation technique is the team using?

An e-learning company in Amman is preparing release planning for a new course-authoring tool. The product owner has just prioritized 40 new user stories, and the team has only one hour to produce rough estimates so the release roadmap can be shared with clients. Rather than numbers, team members place each story into one of five size buckets, XS to XL, by comparing it with stories they have already delivered.

What should the project manager do?

On an ERP rollout for a logistics group in Dubai, the lead integration engineer tells the project manager that she has worked about 60 hours a week for three months to keep up. Her recent code reviews show a rising defect rate, and two other engineers report similar hours. The resource histogram shows integration demand at 140% of available capacity for the next two months, and the go-live date is contractually fixed.

What should the project manager advise?

A ministry of health in Amman has issued an RFP for a hospital laboratory information system. The RFP requires three client references for similar implementations and allows the committee to seek clarification or equivalent evidence through the procurement office. One technically strong bidder declines, stating that its clients are bound by confidentiality, while the other four bidders have submitted references. Bid evaluation is scheduled for next week, and the evaluation committee asks the project manager how to treat this bid.

What should the project manager do with the open risks?

An agile team at a university in Jordan has finished the last iteration of a new HR self-service portal. The product owner confirms that all prioritized backlog items meet the definition of done, and the sponsor is ready to close the project. The risk register still lists three open risks: a pending payroll interface upgrade, a licence renewal next year, and low adoption among part-time staff.

What should the project manager do next?

A hospital information system in Amman is delivered with a hybrid approach. The infrastructure team follows a predictive plan with formal sign-off gates, while two application teams work in two-week sprints. At the first integration point, the application teams wait two weeks for server environment sign-off, and their sprint goals slip. Each side blames the other's method, and the sponsor asks the project manager how integration will work for the rest of the project.

Which interpretation should the project manager present?

A contractor is upgrading a water treatment plant in Alexandria. At the month-six status date, the planned value is EGP 4.5 million, the earned value is EGP 4.0 million, and the actual cost is EGP 3.7 million. The utility's steering committee asks the project manager to explain what these figures mean before it decides whether to approve overtime for the remaining mechanical works.

Which action best addresses the team's concern?

An agile team at a retail bank in Cairo has delivered mobile onboarding features for six sprints. In the retrospective, developers say they no longer know whether their work matters because they only see velocity charts. The product owner has analytics showing that digital account openings rose 18 percent, but this data has never been shared with the team. The sponsor wants the team to stay focused on customer outcomes.

What should the project manager do?

A contractor delivers a pharmacy automation system to a hospital in Kuwait. The system passed all internal QA tests, but during customer acceptance testing the hospital finds two critical defects: incorrect dosage rounding and a label printing failure. The hospital refuses to sign acceptance. The contractor's QA lead says the defects came from test data the hospital supplied late, and the account manager wants to argue the point.

How should the project manager respond?

A university in Jeddah is deploying a new student information system. The data-center hardware installation follows a predictive plan with an approved WBS, while the software configuration is delivered in two-week sprints from a product backlog. At a steering committee meeting, the sponsor asks the project manager to present the scope baseline so the committee can track scope changes for the remainder of the project.

What is the cost performance index (CPI) for this sprint?

A Scrum team at a bank in Bahrain is tracking release finances with agile earned value. For the current sprint, the team planned 50 story points with a budget of $1,000 per point, so planned value is $50,000. Labor costs for the sprint came to $55,000. At the sprint review, the product owner accepted 40 story points as done; the other 10 points failed acceptance tests and returned to the backlog.

How should the project manager respond?

On a hospital extension project in Dammam, the structural steel erection activity has been delayed by three days because the inspection authority rescheduled its visit. The activity lies on the critical path and has zero total float. The approved completion date is fixed in the contract, and the next critical activities are cladding and roofing. The client asks the project manager what the delay means for the completion date.

What should the project manager do?

A business analyst on a pension-system modernization in Muscat has a long-planned family vacation that overlaps the next sprint review. This review will show the first end-to-end calculation flow to the fund's board members, and she prepared most of the scenarios. The leave was approved months ago under company policy. The project manager is concerned that the demonstration will be weaker without her.

What should the project manager do next?

A logistics company in Alexandria licenses a route-planning platform at a per-user rate. The original agreement covered 10 users, but the rollout to regional depots will raise usage to 50 users within six months, multiplying the annual license cost by five. The contract renewal date is three months away, and two competing platforms offer enterprise pricing. The finance manager wants a recommendation.

What should the project manager do?

A water treatment SCADA upgrade in Sharjah is 95% complete. The remaining work is the as-built documentation, operating manuals, and handover training records listed in the contract's acceptance criteria. The team, eager to move to a new project, argues that the real work is done and the client's operators already know the system. The client's maintenance manager has asked twice when the manuals will arrive.

Why is the architect's approach the better delivery choice?

A team at a Qatari airline is starting a new baggage-tracking feature that touches the mobile app, a new API layer, the legacy reservation system, and airport scanners. Integration across these layers has caused late failures on past projects. In sprint planning, the architect proposes beginning with a walking skeleton. Some developers prefer to build and perfect each layer separately before connecting them.

How should the project manager prepare the interim review?

A 30-month metro station package in Jeddah has just reached 50 percent of its baseline duration. The sponsor has requested a formal interim review to decide whether to release the next funding tranche. The project manager has strong cost data showing a CPI of 0.98, but schedule, quality and risk information sit in separate reports owned by different leads, and the benefits forecast has not been updated since the business case was approved.

What should the project manager do?

A ministry of health in the Gulf is deploying a new electronic prescribing system to 120 clinics. The business case projects savings from fewer dispensing errors, but only if pharmacists and physicians use the system correctly from day one. The training budget of USD 180,000 was cut during the annual budget review, and clinic managers warn that without it adoption will be patchy. Go-live is four months away.

What should the Scrum Master do?

An internal quality audit at a Qatari insurance company reviewed the last three sprints of a claims-portal team. It found that some stories were marked done once coded, while others were marked done only after testing and deployment to staging. As a result, the sprint review showed features as complete that stakeholders could not use, and the product owner's release forecasts have been unreliable for a month.

What should the project manager do?

A food manufacturer in Jeddah contracted a vendor to supply and install an inventory tracking system. The vendor delivered exactly what the signed statement of work described, and every acceptance test passed. However, warehouse supervisors now say the system cannot handle batch and expiry-date tracking, which they consider essential. The project manager confirms that this need never appeared in the requirements documentation or the statement of work.

What should the project manager do next?

A utility in Amman is midway through a predictive project to replace its meter-reading system under an approved scope baseline. A technical study completed this month shows that a newly available smart-meter platform makes roughly 30% of the planned customizations unnecessary. The contractor is still building some of those components. The project manager estimates that dropping them could save cost and two months, though contract terms may require compensation for work already started.

What should the project manager do next?

An agile team is building a citizen services portal for a government authority in the GCC. National digital-government regulations require public portals to meet a defined web accessibility conformance level. At the sprint review, a ministry representative asks whether the new booking feature complies, and the team realizes accessibility was never part of its acceptance criteria. Four sprints remain before the public launch date set by the authority.

What should the project manager do?

After a payment outage at a digital wallet provider in Cairo, the operations director wants to identify the engineer who pushed the faulty configuration. A senior team member proposes running a blameless post-incident review instead, focusing on which system conditions allowed the error. Engineers have been reluctant to report near misses since a colleague was formally reprimanded after a previous incident.

What should the project manager do first?

A petrochemical company in Jubail is upgrading its plant control system over eighteen months. The operations vice president, who chairs the design authority and approves every major technical decision, has privately told the project manager that he is likely to retire in about three months. No deputy has been named, and several design decisions planned for month five depend on his judgment and his knowledge of past plant incidents.

What should the Scrum Master do?

A newly hired developer at a software house in Amman proposes that the team move to a four-day work week, citing studies on productivity and wellbeing. Several senior members worry about customer support coverage and contract commitments. The company has no policy on compressed schedules, and the CEO has said leadership is open to well-evidenced proposals for new ways of working.

What should the project manager do?

A hybrid team rolling out a patient-portal for a hospital group in Saudi Arabia keeps waiting on decisions from the executive committee, such as data-retention rules and vendor selection for SMS notifications. Recent decisions have taken three to five weeks, and two sprints have had to swap in lower-value work. At the retrospective, the team says leadership is too slow and the delays are hurting delivery.

What should the project manager do first?

A project manager is leading an ERP rollout for a manufacturing group in Amman when the group announces a merger with a larger regional competitor. The project's sponsor will leave after the merger closes next month, and the combined company will review all capital projects. Team members are anxious about their jobs, and two vendors have asked whether their contracts will be honored.

What should the project manager do?

In a retrospective, an agile team at a software firm in Cairo votes unanimously to trial a four-day work week, citing burnout and strong recent delivery. The firm's HR policy sets a standard five-day week for all employees, and changes require executive approval. Team members ask the project manager to simply let them start next sprint, saying their velocity will prove the idea works.

What should the project manager do next?

On a predictive water-treatment plant expansion in Alexandria, the change control board approves a change that relocates the chemical dosing building to meet a new setback rule. The project manager updates the drawings register, the scope statement and the schedule and cost baselines. The civil subcontractor's crew is due on site in three days, and the procurement lead and the client's operations team still hold copies of the old layout and the old delivery dates.

What should the project manager do immediately?

A project manager at a fintech company in Dubai discovers that the lead engineer of an outsourced development vendor has posted code from the company's proprietary payments engine in his public online portfolio. The vendor contract includes confidentiality and intellectual property clauses, and the company has a legal department. The posts are still publicly visible, and the vendor's team is midway through the current release.

What should the project manager do?

A cloud operations team at a bank in Abu Dhabi recently adopted blameless post-incident reviews. Last week, a configuration change by one engineer caused a two-hour outage of the mobile banking app. At the first review, the engineer looks tense, and a manager from another department has already asked in the chat who made the change. The project manager is facilitating the session.

What should the project manager do?

The sponsor of a national railway signalling upgrade is preparing the annual board presentation. She asks the project manager to delete three high-rated risks from the formal risk register before it is shared, arguing that board members will not understand the technical nuance and might cut funding. The risks are real, have named owners and active mitigation plans. The board pack is due in two days.

What should the Scrum Master do first?

Six months into an agile transformation at a government housing agency in Riyadh, most delivery team members have adopted the new practices. Two experienced analysts still write full specifications up front and skip refinement sessions, saying the old method has always worked. Their work is delaying feedback on two features, and other members are growing frustrated with them.